14 Cartas en este set
- Frente
- Atrás
What do you need to select when you create a maintenance plan that only generates notification(s)?
Please choose the correct answer. a) O A maintenance plan category for notifications b) O A specific notification type for maintenance plans c) O A specific notification type that includes a task list d) O A specific maintenance strategy for notifications |
a) O A maintenance plan category for notifications
|
TRANSACCION/RUTA
Create Maintenance Plan |
Menu path:
Logistics > Plant Maintenance > Preventive Maintenance > Maintenance Planning > Maintenance Plans > Create > Single Cycle Plan Transaction code IP41 – Single Cycle Plan |
Which of the following rules applies to user status in orders and notifications?
Please choose the correct answer. a) O The user status in the notification can be copied into the order. b) O When you set a new user status with a status number, the previous user status with status number is deactivated. c) O When a user status is flagged as an initial status, it overrides the initial system status CRTD. d) O Changes to the user status can affect authorizations. |
b) O When you set a new user status with a status number, the previous user status with status number is deactivated
|
Your customer needs to review costs in a maintenance order at operation level.
Which Customizing steps must you perform? a) O Set the Account Assignment indicator for the settlement profile and assign the settlement profile to the order type. b) O Set the Account Assignment indicator for the valuation variant and assign the valuation variant to the cost variant. c) O Set the Account Assignment indicator for the order type and assign the order type to the plants. d) O Set the Account Assignment indicator for the costing sheet and assign the costing sheet to the order type. |
c) O Set the Account Assignment indicator for the order type and assign the order type to the plants.
|
Your customer wants to assign maintenance orders to network activities automatically with the Maintenance Event Builder (MEB). Which of the following steps must you perform? Note:
There are 2 correct answers to this question. a) O Assign a network to a revision with revision type WPS-Controlled. b) O Assign a hierarchical task list to a notification. c) O Assign the Reference PM/PS element to task list headers and network activities. d) O Assign maintenance orders manually to a revision with revision type WPS-Controlled. 10. |
a) O Assign a network to a revision with revision type WPS-Controlled.
c) O Assign the Reference PM/PS element to task list headers and network activities. |
10. How are the planned costs for a refurbished part or parts displayed in the planned/actual order report?
Please choose the correct answer. a) O As revenue with a positive value b) O As costs with a negative value c) O As revenue with a negative value d) O As costs with a positive value |
b) O As costs with a negative value
|
Your customer wants to view a list of all planned materials in multiple maintenance orders with order status CRTD. Which of the following standard reports can you use to find the information required?
Note: There are 3 correct answers to this question. a) O The materials where-used report b) O The order and operation list c) O The material availability reportInsured o Insurer d) O The operation list e) O The order list 2. |
b) O The order and operation list
c) O The material availability reportInsured o Insurer e) O The order list 2. |
4. Which of the following item categories can you use in a Plant Maintenance bill of material (BOM)?
Note: There are 2 correct answers to this question. a) O Stock material b) O Equipment c) O Assembly d) O Non-stock material |
a) O Stock material
d) O Non-stock material |
IP41
|
Maintenance Plan
|
IP10
|
Generar OM-s
|
IW39
|
Display PM orders
|
IP15
|
Change Maintenance Plan
|
IP16
|
Display Maintenance Plan
|
IP24
|
Scheduling overview list form
|